Single residential connection
Who is this for?
For a single home with or without an existing connection, wanting to connect via underground.
How long will it take?
3 months to provide you with a technical assessment
4-6 months to provide you with a design and quote, depending on the complexity of your project
3 months to construct, upon payment of quote and confirmation your site is ready
How much will it cost?
We'll provide a quote after we complete the scoping and design of your project.
Overhead to underground conversion eligible for fixed price
Your property is on the same side of the road as the point of connection to the electricity network | $3,400 |
Your property is on the opposite side of the road to the point of connection to the electricity network | $4,900 |
If a suitable location for a pillar installation can't be provided we may offer a below ground service pit for the connection point. This will incur additional costs specific to the installation circumstances. Additional site preparation requirements also apply.
Application fee
Application fee (plus 0.59% credit card surcharge) | $497.42 |
Design fee
Project complexity | Fee |
---|---|
Standard | $1,320 |
Detailed | $3,300 |
Complex | $6,600 |
* While the design fee is GST inclusive, the GST exclusive amount will be deducted from the access offer if proceeding, i.e. GST is not refunded
Other fees
Description | Fee |
---|---|
Construction costs | We will provide a quote |
Cancellation fee | $550 |
The cost of an electricity supply is dependent on how much power you require. In most cases, the cost will be based on what we call the Distribution Low Voltage Connection Scheme.
FAQs
Strata schemes typically have a single connection point to the Western Power network that determines the total allocation of available electricity supply and generation capacity to be shared by all strata lots.
This connection point has a fixed capacity, so it's important for strata lot owners and prospective purchasers to be aware of the arrangements and obligations relating to the connection, as it may restrict their ability to install equipment such as home EV charging stations, rooftop solar panels and batteries.
Before applying to connect this type of equipment, strata lot owners should first seek permission from their strata company to use an allocation of the total network capacity allocated to the strata scheme.
Failing to do this may prevent other strata lot owners from connecting their own equipment, or require the strata company to upgrade the connection to the Western Power network to accommodate the needs of all strata lot owners.
It's important to remember that the strata company is ultimately responsible for the management of the common connection to the Western Power network and the common electrical system within the strata scheme. Effective management of this shared resource will allow the benefits of renewable energy solutions to be shared by the all strata lot owners.
More information about strata titling principles can be found in Landgate's Guide to strata titles.
See also: How do I apply for solar power in a lifestyle village, large strata or other multi-residential site?
Western Power is regulated by the state government in terms of how it can earn revenue. Our revenue (through tariffs) is determined by the size of our Regulated Asset Base (RAB).
When streetlights are added to the RAB they have an economic life of 20 years. If a streetlight is replaced or upgraded to LED lighting when it is younger than 20 years old, there’s still some value in there that we haven’t recovered back yet.
Sometimes your circumstances change and you may need to cancel or change the information within your application after you have submitted it to us.
If you wish to change the scope of work in your application we will first review the change and then either:
- continue the project with the variation and invoice you for any additional materials, design work and remobilisation costs incurred. We will typically only take this approach when the change is very minor.
or
- if the change is significant we will cancel your project. You will need to submit a new application with your new requirements.
For cancelled applications we will invoice you for the costs incurred up to the point of cancellation (time and materials). If construction work has already commenced we will refund the difference from your access offer less any costs incurred.
If you require a new connection at your property within 10 years of poles and wires being decommissioned, we will connect your property in accordance with the Electricity Industry (Obligation to Connect) Regulations (2005). As the traditional overhead network will be decommissioned, any new connection at this location will be serviced by a SPS.
To ensure you are not disadvantaged by the removal of the overhead network, we will preserve the network equivalent connection costs for new connection applications for premises within 100 metres of the removed poles and wires, for a period of two years from the date of notification of our intention to decommission the network. This means, if you need a new connection at your property where network infrastructure is scheduled for removal or has already been removed, you will be able to receive that new connection at the lowest cost – either a network equivalent cost or SPS cost, whichever is lower. After the two-year period has expired, any new customers will be required to pay the full cost of an SPS connection.
The preservation of connection costs is attached to the land, not the customer. For example, in cases where an eligible customer decides to sell or subdivide their land, the new landowner(s) of the property or the subdivided land parcels are eligible for the preserved network connection costs if they have bought the property and applied for a new connection within two years of the customer communication regarding decommissioning being sent.
To be eligible to receive a new connection at the ‘lowest cost’ during this period, you will need to provide all relevant planning information (including, but not limited to, building permits, development plans and approvals or certified electrical loads) when applying for a new connection.
For more information, please contact us.
You will be charged a design fee upon lodging your application.
Once your project proceeds to construction phase the design fee, excluding GST, is deducted from the price on your Access Offer and Acceptance.