Indicative timeline
Activity | Timeline |
---|---|
Consultation with local governments and State Government agencies | In progress from mid-2023 |
Flora and fauna survey | In progress from late-2023 |
Engagement with landowners and community | Proposed from early-2024 |
Refer project to State and Federal environmental regulatory bodies | From mid-2024 |
Environmental impact assessment | From mid-2024 |
Submit Aboriginal Heritage Act approval | Proposed 2024 |
Submit developmental approvals | Proposed 2024 |
Procurement of materials | Proposed from 2025 |
Finalise environment, heritage and planning approvals | Proposed 2026 |
*The timelines indicated are subject to change as a result of relevant surveys and assessments. Some activities may happen ahead of approvals.