Northern Terminal to Three Springs Terminal
This proposed package of work will significantly improve the flow of renewable energy to and from the area. It includes conversion of 290 kms of existing 132 kV transmission line to 330 kV, from Northern Terminal in Malaga to substations at Pinjar, Regans, Cataby, Eneabba and then Three Springs, and a new double circuit transmission line between Eneabba and Eneabba Terminal.
Additionally, new a 330 kV terminal will be constructed next to the existing Regans Substation, with connections to the two 330 kV transmission lines passing near the site to facilitate the resupply of Regans 132 kV Substation.
*The map is a simple representation - location is indicative. All new line routes are subject to further design and route selection.
Indicative timeline
Activity | Timeline |
---|---|
Flora and fauna survey | In progress now |
Procurement of materials | In progress now |
Consultation with local governments and State Government agencies | In progress from mid-2023 |
Cultural heritage assessment | In progress from mid-2023 |
Engagement with landowners and community | Proposed from late-2023 |
Environmental impact assessment | Proposed from mid-2024 |
Refer project to State and Federal environmental regulatory bodies | From mid-2024 |
Submit Aboriginal Heritage Act approval | Proposed 2024 |
Submit developmental approvals | Proposed 2024 |
Finalise environment, heritage and planning approvals | Proposed 2026 |
*The timelines indicated are subject to change as a result of relevant surveys and assessments. Some activities may happen ahead of approvals.