The high voltage (HV) subdivision pool allows the cost of installing HV infrastructure to be shared among developers of residential subdivisions. The pool reimburses developers who have paid for more than their share of the HV infrastructure, and collects funds from developers who make use of excess capacity on that infrastructure.
HV subdivision pool charges and parameters
This table outlines current charges and parameters under which the HV pool operates. These are updated every six months or when the HV pool balance is seen to be trending towards a larger deficit balance, whichever comes first.
Baseline Accumulated HV Pool Payment * | Size and units |
---|---|
System Charge Rate * |
$175 /kVA |
Baseline Accumulated HV Pool Payment * |
$5,067,968 |
Baseline Accumulated Design Load * |
31,713 kVA |
Baseline System Charge * |
$160 /kVA |
Date of the HV Pool System Charge Reset |
01/01/2024 |
Accumulated HV Pool Payments* |
$246,111,358 |
Accumulated HV Pool Charges* |
$256,552,514 |
Accumulated Design Load* |
993,247 kVA |
* at the time of system charge re-set