Direct connection into an unmetered supply
Red spot fuse
Who is this for?
For local Government authorities, government agencies and approved providers of specialised services.
How long will it take?
Up to 10 business days to respond to your application.
After our technical assessment we’ll contact you to discuss your requirements and work with you on an expected delivery date in line with the complexity of your project.
How much will it cost?
$781
A registered electrical contractor will need to submit this application.
Application process
You’ve applied
1
You’ll receive a scope
2
You’ll receive design fee invoice
3
You’ll receive a quote for the delivery of the works
4
Let us know how we went
5
What to include with your application
A site plan
Provides us with an understanding of your work site, the location of existing and new assets and help us to design your product. It will need to include:
- Your property
- Neighbouring properties
- The location of the supply point
Site photos
Help us understand your current connection arrangements and more easily identify potential site specific issues. Photos will need to include:
- The extent of the worksite
- Any obstructions in the area
Equipment schedule
An equipment schedule allows us to notify the electricity retailer of the new/changed load of the UMS connection; and, check that the load does not exceed 4.8kW (20A) single phase.
Ready to apply for a direct connection into an unmetered supply?
Once you’ve gotten the above, you are ready to apply.