Contracts, costs and timeframes
Contracts, costs and timeframes
The table below summarises the Western Power contract(s) used, indicative cost and timeframe estimates, and the Western Power deliverable customers will receive, for each activity during the various stages of the connection process.
Please note, all Western Power time spent on your project is cost recoverable and will be reconciled based on actuals upon completion of the work. Work will not commence until payment has been received. The estimated costs and timeframes shown above are to be used as a guide and will vary depending on project specifics, such as facility size, connection voltage, complexity and geographic etc. Some of these activities can be conducted concurrently so the information above is not an indication of the total duration of all activities. These timings do not factor in queuing times, waiting for payment and delay to customer deliverables.
In addition to these costs, each relevant contract throughout the process will contain Management Support costs to cover the Western Power project support and management resources required to support the delivery of the customer project processing works, including but not limited to administration of contracts, preparing project documentation and deliverables, meetings and communication with the customer, and ongoing sponsorship of the customer Enquiry/Connection Application within Western Power. These cost estimates will be based on an allowance of up to 8 hours per week over the duration of the contracted timeframe.
Following the cancellation, expiry, termination or variation of any invoice the applicant may be liable to pay an administration fee of $550 (inclusive of GST).
A generic schedule containing all the connection process activities, timeframes and customer deliverables can be found here. This will be tailored to your project once we have received and assessed your Connection Application as being complete.
Stage | Contract | Activity | Estimate cost* (excluding GST) | Estimate timeframe* | WP deliverable(s) to customers |
---|---|---|---|---|---|
Enquiry | Enquiry Processing Contract (EPC) | Connection Options Assessment | $25,000 | 8 weeks | Connection Options Assessment Pack |
Initiation | Processing Proposal Contract (PPC) | Connection Application Fee | $5,000 | 20 business days | Connection Application Data Assessment |
Initiation | Processing Proposal Contract (PPC) | Connection Options Assessment (if required) | $25,000 | 8 weeks | Connection Options Assessment Pack |
Initiation | Processing Proposal Contract (PPC)
|
Steady State Study (If Western Power completes study)
-or- Steady State Study – Due diligence Review (If Western Power reviews customer self-serve study) |
$35,000
-or- $25,000 |
10 weeks
-or- 6 weeks |
Steady State Study Report
-or- Feedback on customers Steady State Study Report |
Initiation | Processing Proposal Contract (PPC) | Grid Input Package (Generators only) | $30,000 | 8 weeks | Grid Input Package |
Initiation | Processing Proposal Contract (PPC) | Model Due Diligence
-and- GPS Assessment R0 Validation (Generators only) |
$10,000
-and- $15,000 |
2 weeks
-and- 8 weeks |
GPS Assessment Report |
Initiation | Processing Proposal Contract (PPC) | Load Model Assessment (If Western Power completes assessment)
-or- Load Model Due Diligence (If Western Power reviews customer self-serve assessment) |
$30,000
-or- $10,000 |
8 weeks
-or- 2 weeks |
Load Model Assessment Report
-or- Feedback on customers Load Model Assessment Report |
Initiation | Processing Proposal Contract (PPC) | Community Engagement and Environmental Desktop Assessment | $15,000 | 2 weeks | Community Engagement Desktop Assessment Environmental, Land and Heritage Desktop Assessment |
Initiation | Processing Proposal Contract (PPC) | Scope Definition | $30,000 | 5 weeks | Scope Definition Report |
Scoping | Processing Proposal Contract (PPC) | Project scoping including Concept Design and Class 4 Estimate
-or- Project scoping including Concept Design and Class 3 Estimate |
$75,000 - $350,000
-or- $100,000 - $410,000 |
16 – 24 weeks
-or- 18 – 28 weeks |
Project Scoping Report |
Planning | Processing Proposal Contract (PPC) | Access Offer Preparation | $55,000 | 14 weeks |
Interconnection Works Contract (IWC) Electricity Transfer Access Contract (ETAC) |
Execution | Interconnection Works Contract (IWC)
Tripartite Deed (PPC) |
Dynamic Studies | $55,000 | 10 weeks | Dynamic Studies Report |
Execution | Interconnection Works Contract (IWC)
Tripartite Deed (PPC) |
EMT Studies Stage 1 | $30,000 | 5 weeks | EMT Studies Report (Stage 1) |
Execution | Interconnection Works Contract (IWC)
Tripartite Deed (PPC) |
EMT Studies Stage 2 | $55,000 | 10 weeks | Updated EMT Studies Report (Stage 2) |
Execution | Interconnection Works Contract (IWC)
Tripartite Deed (PPC) |
Detailed Design | Project Specific | Project Specific | N/A |
Execution | Interconnection Works Contract (IWC)
Electricity Transfer Access Contract (ETAC) Tripartite Deed (PPC) |
Procurement, Construction and Commissioning (including GPS Assessment R1 & R2 Validation), and Project Close Out | Project Specific | Project Specific | Practical Completion Approval to Operate |
Execution | Interconnection Works Contract (IWC)
Electricity Transfer Access Contract (ETAC) |
Non-thermal Limits Equation Study | up to $40,000 | up to 8 weeks | Non-Thermal Limits Equation Study report |