Move or remove a green dome

share icon

Who is this for?

For people wanting to move or remove a green dome (mini pillar or uni pillar), the point of connection between your property and the main electrical network that runs along your street.

clock icon

How long will it take?

3 months to provide you with a technical assessment

4-6 months to provide you with a design and quote, depending on the complexity of your project

3 months to construct, upon payment of quote and confirmation your site is ready

*Timeframes indicative only and subject to change based on demand.

dollar icon

How much will it cost?

We'll provide a quote after we complete the scoping and design of your project.

 

 

Application fee

Application fee (plus 0.59% credit card surcharge) $497.42

 

Design fee

Project complexity Design fee
Standard $1,320
Detailed $3,300
Complex $6,600

* While the design fee is GST inclusive, the GST exclusive amount will be deducted from the access offer if proceeding, i.e. GST is not refunded

 

Other fees

Description Fee
Construction costs We will provide a quote
Cancellation fee $550

 

Application process

You’ve applied
1

We’ll contact you to discuss your application.

You’ll receive a scope
2

After our technical assessment we’ll confirm the scope of works with you.

You’ll receive design fee invoice
3

Once payment is received, we will design the project to your needs.

You’ll receive a quote for the delivery of the works
4

After the acceptance and payment is received, we’ll schedule the works for delivery. Schedules are dependent on your location and the complexity of our work.

Let us know how we went
5

Your feedback is importance to help ensure we’re meeting your needs and expectations.

What to include with your application

circle check orange

A site plan

Provides us with an understanding of your work site, the location of existing and new assets and help us to design your product. It will need to include:

  • Your property
  • Neighbouring properties
  • The location of the supply point
circle check orange

Site photos

Help us understand your current connection arrangements and more easily identify potential site-specific issues. Photos will need to include:

  • The extent of the worksite
  • Any obstructions in the area
circle check orange

Neighbours authority

If your project will impact your neighbour’s property by having new assets installed or relocated on or in front of their property, you’ll need their authorisation.

Ready to move or remove a green dome?

Once you’ve gotten the above, you are ready to apply.