Who is this for?
For people wanting to move or remove a green dome (mini pillar or uni pillar), the point of connection between your property and the main electrical network that runs along your street.
How long will it take?
3 months to provide you with a technical assessment
4-6 months to provide you with a design and quote, depending on the complexity of your project
3 months to construct, upon payment of quote and confirmation your site is ready
How much will it cost?
We'll provide a quote after we complete the scoping and design of your project.
Application fee
Application fee (plus 0.59% credit card surcharge) | $497.42 |
Design fee
Project complexity | Design fee |
---|---|
Standard | $1,320 |
Detailed | $3,300 |
Complex | $6,600 |
* While the design fee is GST inclusive, the GST exclusive amount will be deducted from the access offer if proceeding, i.e. GST is not refunded
Other fees
Description | Fee |
---|---|
Construction costs | We will provide a quote |
Cancellation fee | $550 |
Application process
You’ve applied
1
You’ll receive a scope
2
You’ll receive design fee invoice
3
You’ll receive a quote for the delivery of the works
4
Let us know how we went
5
What to include with your application
A site plan
Provides us with an understanding of your work site, the location of existing and new assets and help us to design your product. It will need to include:
- Your property
- Neighbouring properties
- The location of the supply point
Site photos
Help us understand your current connection arrangements and more easily identify potential site-specific issues. Photos will need to include:
- The extent of the worksite
- Any obstructions in the area
Neighbours authority
If your project will impact your neighbour’s property by having new assets installed or relocated on or in front of their property, you’ll need their authorisation.
Ready to move or remove a green dome?
Once you’ve gotten the above, you are ready to apply.
FAQs
You may have seen a green dome (also known as a green pillar) on your property or in your neighbourhood and wondered, what does a green dome do and why do I have one?
Green domes play an important role in delivering electricity to you – it is the point of connection between your property and the main electrical network that runs along your street.
It is the same electrical wiring that runs from power poles to the top of houses, except underground. The green dome acts as a protective housing for the electrical wires that feed a property.
They are primarily found in areas where there is an underground power supply.
Green domes can be found in areas with overhead power poles and wires, in particular public areas like parks and roadsides, or where new houses have been built in the area (as all new subdivisions must install underground power connections).
It’s easy to miss them, as they are coloured green to blend in with natural surrounds, however it is important to remember that they play an important role in supplying your property with power and, if damaged, pose the same risk as a downed powerline. If you see a damaged green dome, it is important you report it to Western Power immediately on 13 13 51.
You can also apply to relocate your green dome or convert your overhead power supply to underground.
Green domes should be clear and accessible at all times so that our crews or electrical contractors can access the electrical wiring as needed.
We may require access to repair/isolate power in an emergency, repair a fault, replace a damaged green dome cover or change the position of your electricity supply. By having the green domes visible and clear of interference, we can maintain and isolate the underground power with minimal disruption to customers.
To ensure access, green domes should be kept vertically unimpeded and have a 500mm clearance zone around the base of the unit. This includes installations such as fences or vegetation.
If the green dome has limited or poor access, it may result in delays to restoring your power during faults.
This clearance zone also ensures the green dome and its electrical wiring has sufficient ventilation to operate efficiently and safely.
Human interference is the main cause of damage to green domes.
This includes vehicles driving into or over the green dome, construction/building activity, landscaping activity and people playing or jumping on the green dome.
Grass or bushfires also lead to green dome damage.
You will be charged a design fee upon lodging your application.
Once your project proceeds to construction phase the design fee, excluding GST, is deducted from the price on your Access Offer and Acceptance.
Sometimes your circumstances change and you may need to cancel or change the information within your application after you have submitted it to us.
If you wish to change the scope of work in your application we will first review the change and then either:
- continue the project with the variation and invoice you for any additional materials, design work and remobilisation costs incurred. We will typically only take this approach when the change is very minor.
or
- if the change is significant we will cancel your project. You will need to submit a new application with your new requirements.