Increase medium commercial connection
Who is this for?
For commercial properties who want to upgrade the electricity supply to a maximum demand greater than 250A/180kva but no greater than 1300A/1000kVA.
How long will it take?
3 months to provide you with a technical assessment.
7 -9 months to provide you with a design and quote, depending on the complexity of your project.
3 months to construct, upon payment of quote and confirmation your site is ready.
How much will it cost?
We'll provide a quote after we complete the scoping and design of your project.
Application process
You’ve applied
1
You’ll receive a scope
2
You’ll receive design fee invoice
3
You’ll receive a quote for the delivery of the works
4
Let us know how we went
5
What to include with your application
A CAD site plan
Your CAD plan helps us better understand your work site and location of assets. We extract data from your plan to assist us with your design.
For a CAD site plan to be accepted, it must clearly show:
- the proposed pillar location in a visible colour on the site plan.
- the street name on which the property borders
- the full address of the property
- the nearest intersection (for rural properties it helps to locate the site)
In order to provide a fast, accurate quote and advice on your new connection arrangement we require a comprehensive site plan with details of your current and/or proposed site layout. This includes but is not limited to the following information being clearly marked on your plan:
- boundary or retaining walls at the side and front of the property – including depth of wall
- location of items such as letterboxes, garden beds, trees/stumps, driveways, crossovers
- detail or grades of any major inclines or slopes near the front boundary
- utility locations for water meters/pipes, gas pipes, sewer mains/connections and access points
- proposed location of new pillar/s
Example site plan
Pillar exclusion zone
The pillar needs to have an exclusion zone of 50cm from its centre. Inside or under the exclusion zone there must not be any:
- water pipes, water storage facilities or water meters
- gas pipes or meters
- telecommunication cables
- sewage, waste water, or storm water pipes
- reticulation pipes or cables
- tree roots and other vegetation
- concrete, asphalt, limestone or bedrock
Find out what underground assets may be in the vicinity by submitting a Dial Before You Dig application.
Site photos
Help us understand your current connection arrangements and more easily identify potential site specific issues. Photos will need to include:
- The extent of the worksite
- Any obstructions in the area
Site photos help us understand your current connection arrangements and more easily identify potential site specific issues. If you’re able to supply us with a close up and wide photos it will potentially reduce application times as we won’t be required to visit the site.
Example close up photo
Example wide photo
Single line diagram
The single line diagram provides us with the technical information to design a connection to meet your requirements.
In your single line diagram, you'll need to include:
- mains size
- number of cables per phase
- service protection device (SPD) setting and rating
- metering types
- metering quantity.
Load breakdown
Your load breakdown allows us to assess the impact your project will have on the network. It also allows us to apply the appropriate charging policy.
Disturbing loads
The information allows us to check the impact of your loads on the network. You must comply with Power Quality limits as per AS/NZS 61000.3.11, SA-SNZ TR IEC 61000.3.14 and Western Power Technical Rules.
Statement of compliance to AS61000.3.6
Your accredited electrical contractor or consultant must submit a statement verifying that the installation complies with AS/NZS 61000.3.11, SA-SNZ TR IEC 61000.3.14 and Western Power’s Technical Rules.
Revenue offset
If a customer would like to be considered for revenue offset, some information is required at the technial assessment stage. See our revenue offset FAQs for more information.
Your support documents will help us determine the future increase in electricity consumption at your site so we can confidently apply revenue offset to subsidise the upfront customer contribution.
Ready to apply for an increase to a medium commercial connection?
Once you’ve gotten the above, you are ready to apply.
FAQs
You will be charged a design fee upon lodging your application.
Once your project proceeds to construction phase the design fee, excluding GST, is deducted from the price on your Access Offer and Acceptance.
Sometimes your circumstances change and you may need to cancel or change the information within your application after you have submitted it to us.
If you wish to change the scope of work in your application we will first review the change and then either:
- continue the project with the variation and invoice you for any additional materials, design work and remobilisation costs incurred. We will typically only take this approach when the change is very minor.
or
- if the change is significant we will cancel your project. You will need to submit a new application with your new requirements.
For cancelled applications we will invoice you for the costs incurred up to the point of cancellation (time and materials). If construction work has already commenced we will refund the difference from your access offer less any costs incurred.