Increase large commercial connection
Who is this for?
For people wanting to upgrade the electricity supply to a maximum demand greater than 1300A/1000kVA.
How long will it take?
3 months to provide you with a technical assessment
8-12 months to provide you with a design and quote, depending on the complexity of your project
3 months to construct, upon payment of quote and confirmation your site is ready
How much will it cost?
We'll provide a quote after we complete the scoping and design of your project.
Application process
You’ve applied
1
You’ll receive a scope
2
You’ll receive design fee invoice
3
You’ll receive a quote for the delivery of the works
4
Let us know how we went
5
What to include with your application
A site plan
Provides us with an understanding of your work site, the location of existing and new assets and help us to design your product. It will need to include:
- Your property
- Neighbouring properties
- The location of the supply point
Site photos
Help us understand your current connection arrangements and more easily identify potential site specific issues. Photos will need to include:
- The extent of the worksite
- Any obstructions in the area
Neighbours authority
If your project will impact your neighbour’s property by having new assets installed or relocated on or in front of their property, you’ll need their authorisation.
Ready to apply for an increase to a large commercial connection?
Once you’ve gotten the above, you are ready to apply.