Improving the reliability of power in the town of Perenjori

Perenjori: From blackout town to energy innovation crown

Blackouts have been all too common in the small Western Australian town of Perenjori, 150km east of Dongara.

The Mid West town sits at the end of a long stretch of powerlines which are exposed to a range of environmental factors.

A problem anywhere along this long line could cut power to the town.

Thanks to a 1MWh network battery installed on the outskirts of town, power outages will no longer be a regular occurrence. 

  • Powering up the end of the line

    Back in 2016, if you were living in the town of Perenjori, power outages were a fact of life.  But with the battery energy storage system, these will be a thing of the past. 

    Read on to find out more...

  • Perenjori ready for BESS solution

    Perenjori is reliant on a long feeder line for their power needs which would lead to frequent unplanned power outages. But now they have the BESS solution available to improve power reliability... 

    Read on to find out more...

Project statistics
The 1MWh network battery will act as a backup power supply for the town and will eliminate up to 80% of outages, based on the town’s power outage history.
23 hours
Decrease in total outage time
50%
Decrease in total number of outages
55%
Decrease in length of outages
Immediately
Customers notified of an outage

Benefits of the Perenjori BESS

Perenjori is the first town to trial a backup battery supply on the Western Power network. The battery was commissioned in August 2018 and the community is already beginning to experience tangible benefits.

We have been working with Balance Utility Solutions to design and deliver the Battery Energy Storage System. The system is comprised of lithium-ion batteries with an inverter. It kicks into gear instantaneously if the town loses supply from the main electricity network.

Batteries a big part of WA's future grid

The 1MWh network battery will act as a backup power supply for the town and will eliminate up to 80% of outages, based on the town's power outage history.

Town residents and businesses may still experience power outages, however these will be after the network battery is exhausted and a series of notifications will enable them to plan for the outage.

Insights gained from this trial are helping us determine how we can deploy network batteries effectively to other communities.