Temporary power

Temporary power supply allows builders and trades to work when there is no permanent connection to the site. To set up a temporary supply account contact your retailer and then refer to the options below.

It is often more cost effective to install a permanent supply straight away.  To do this, go to New connections.

Use this service if you want

To install temporary supply in an area with existing underground power

To install a temporary supply with above standard power requirements

How long will it take?

  • Within 5 business days in the Perth metro and major regional towns
  • Within 7 business days in country and rural areas
  • 3 weeks to provide you with a quote
  • 10 weeks to build once payment is received

What if I change my mind or want to cancel my application?

 Learn more

Learn more

What more do I need to know?

 

Learn more

What will I need to complete this application?

 

How much will it cost?

$553.24 

We will provide you with a quote

Fees and charges

Following the cancellation, expiry, termination or variation of the Customer Work Request or any other aspect of the works or documentation relating to the works, the customer may be liable to pay an administration fee of $550 (inclusive of GST) and any additional costs incurred by Western Power.  Further information can be found in our Terms and Conditions clauses 8 and 16.3.

 

Find out more and apply

Apply here

Was this page helpful?YesNo

How can we improve this page

We'd love to hear what you didn't like or how we can improve this page.

Thanks for the feedback

Thanks for the feedback

We're always trying to find ways to improve our customer service.