Skip to content

Remove or relocate a high voltage pole

Changes to application and design fees

On 16 August 2019, we'll introduce a revised fee structure that includes an upfront application fee, new designs fees, and revised information/conformance services fees for all distribution customer projects. Find out more.

Use this service if you want us to relocate or permanently remove high voltage pole.

How long will it take?

  • 7 weeks to provide you with a quote
  • 10 weeks to remove or relocate once payment is received

What will I need to complete this application?

Electricity connections can be varied and complex. We recommend that a professional electrical consultant or contractor completes this application.

You'll need to the following to submit an application:

How much will it cost?

  • Application fee - $495 ex. GST
  • Design fee (ex. GST component deducted from access offer):
    • Standard - $1,320 ex. GST
    • Detailed - $3,300 ex. GST
    • Complex - $6,600 ex. GST
  • Construction - we will provide you with a quote.
  • Cancellation fee - $550 incl. GST

Remove or relocate a high voltage pole

Approximate time required to complete application: 10 minutes.

Apply here