Large scale relocation or removal

Large scale relocations or removals

Approximate time required to complete application: 10 minutes.

Apply here

Use this service if you want us to relocate or permanently remove large portions of equipment not covered by smaller services.

How long will it take?

  • 7 weeks to provide you with a quote
    10 weeks to remove or relocate once payment is received

What if I change my mind or want to cancel my application?

View our FAQ regarding change and cancellation of applications.

What more do I need to know?

  • This service covers a wide range of possibilities, if you are unsure about how to proceed, please consider beginning with a feasibility study
  • There are some physical clearances that are required between the electricity network and your equipment
  • If you want to relocate Western Power equipment onto a neighbour’s property you will need to include their written approval with your application. If there are third party assets (e.g. telecommunication equipment) on a pole flagged for relocation or removal, we will organise for them to be relocated; these costs will appear in your quote
  • We no longer install new overhead assets in metropolitan/built up areas. If your work requires the relocation of overhead assets, they will need to go underground
  • If your work will result in other customers' electricity supplies being relocated underground, you will need to negotiate suitable pillar locations and engage an electrical contractor to complete the connection
  • If your consumer mains are larger than 35mm2, we will need to terminate them for you instead

Substation site

  • If you would like to relocate a substation or pole top transformer you will need to provide land for the new location. If you are unsure about where a substation site can go please submit a feasibility study and one of our consultant engineers will help you you in find a solution
  • When you’re considering your substation site, please read the Western Power Distribution Substation Manual
  • If you would like to apply for a non-compliant site please submit a feasibility study and one of our consultant engineers will let you know if it can be used
  • The final specifications for the substation requirements will be determined when our engineers create your design. This means that the substation site you provide may be subject to change
  • We will install the substation as part of the construction works; however you will need to prepare the site in advance. Some assistance in this can be found in the Western Australian Distribution Connections Manual

What will I need to complete this application?

  • CAD plan
  • Neighbours authority

How much will it cost?

Costs for this vary depending on your scope of work; unfortunately we are unable to provide an estimate before understanding your requirements.

Fees and charges

Following the cancellation, expiry, termination or variation of the Customer Work Request or any other aspect of the works or documentation relating to the works, the customer may be liable to pay an administration fee of $550 (inclusive of GST) and any additional costs incurred by Western Power. Further information can be found in our Terms and Conditions clauses 8 and 16.3.

Large scale relocations or removals

Approximate time required to complete application: 10 minutes.

Apply here