Skip Navigation

Project history

In August 2008 Western Power adopted a fresh approach to the Eastern Terminal project. The project was announced as Powering Perth's Communities (PPC), reflecting that the project would deliver benefits to the entire Perth community, including the Hills area.
Two critical objectives of the PPC project were identified to ensure sufficient power was available in the network and that the security of the network was not compromised.

  1. The delivery of an additional 1000 MW of power to the network by 2011 via a reconstructed 330 kV line from the southwest to Hackett's Gully in the Perth Hills in conjunction with the development of South Eastern Terminal (near Byford), and
  2. The ability to connect this line to a new or existing switchyard by 2017. Switchyards enable Western Power to connect and isolate powerlines, maximising the security of the network.

The PPC project means a more secure power supply for Perth's communities, including our hospitals, schools, businesses and your home.

Two distinct phases of the PPC project were defined, reflecting these two objectives.

Phase I planning is now complete. Phase I involved working with a Focus Group to evaluate a range of tie-in options, taking into account a environmental, technical and visual considerations. This evaluation led to the decision to tie in the new line via a gantry at Hacketts Gully.

Construction on the new line between Wells Terminal and Hacketts Gully will commence at the southern end in late 2009, with the tie-in works in Hacketts Gully scheduled to be completed in late 2011.

 Phase II will involve identifying an appropriate switchyard solution by the end of 2012.   

News archive

A fresh start

Focus Group formed

Community Interest Group presentations

Community Focus Group outcomes

Western Power announces the tie-in option

Western Power would like to announce that Option 1, which involves installing a gantry and extra single pole at the intersection of Mundaring Weir and Bahen Roads in Hacketts Gully, will be used to link a new major power line to the existing grid.

In coming to this decision, Western Power considered the social, environmental, technical and economic issues as well as the recommendations from the Focus Group meeting held in November 2008. The decision is discussed in detail in the 'Powering Perth's Communities Phase I - Outcomes Summary' document (available for download below).

The Focus Group, while not endorsing the project, confirmed that it preferred two possible options for connecting the lines. These were Option 6A and Option 1, with preference for Option 6A. The two options are the same except that an existing tower would be replaced with a similar height pole in Option 6A.

When reviewing the two options comparatively Western Power found that Option 6A had a greater impact with regard to safety, cost, risk to power supplies, risk of traffic interruption during work and land clearing. For these reasons Western Power determined that Option 1 was the preferred tie-in solution.

In addition to the community consultation, Western Power will be submitting Regulatory Test and New Facilities Investment Test (NFIT) applications for determination by the Economic Regulatory Authority (ERA) for this project.  These tests consider the technical and economic implications of a number of alternatives to ensure that the most economically efficient alternative is adopted.  The applications will be based on the South West 330 kV Bulk Transmission Reinforcement - Discussion Paper and will consider submissions made to Western Power forthcoming from our Invitation for submissions - Proposed 330 kV South West Transmission Reinforcement which was open for industry comment from 17 December 2008 to 9 January 2009.

An environmental and social review of the transmission line routes associated with the two main transmission line route alternatives outlined in this discussion paper has also been undertaken (available for download below).

Subject to Regulatory Test and NFIT approval, the next stage in this project will be the construction of the new transmission line between Wells Terminal and Hacketts Gully which is planned to commence in late 2009, at the southern end, with the tie-in works in Hacketts Gully scheduled to be completed in late 2011.

In addition, Western Power will begin consulting with the wider Perth community on Phase II of the PPC project to examine ways to connect the new line into a new or existing switchyard when required in the future.

More information 

For more information please contact ppc@westernpower.com.au or call (08) 9326 4007

Subscribe to Projects RSS Feed

To view PDF files you will need Adobe Acrobat Reader.

Customers with accessibility issues.

Page update on 2 April 2009