Skip Navigation

Confirmed corridor option

The Grey Corridor option (the western most option of the three considered) outperformed all other corridor options and was recommended by Strategen.

This announcement followed six months of stakeholder consultation including; local community, state and local government authorities, industry and environmental representatives as well as specialist and local interest groups.

By collating stakeholder input with detailed analysis, three main corridor options were identified (with several derivatives) to pass through areas with the least number of constraints.

A sustainability assessment considered social, environmental, economic and technical factors and determined the Grey Corridor as having the least overall impact. With the exception of the technical factors, the weighting (importance) of these factors was determined by the community and stakeholders.

Western Power is committed to delivering power transmission solutions based on transparent process and as such relied on the independent work of Strategen to facilitate this process. When undertaking a project such as this, Western Power faces the challenge of carefully balancing the competing needs of various stakeholders, and the wider community.

Final report

Appendicies and figures

Page update on 11 February 2008